Highway 413 is a 52 km corridor from Highway 400 in Vaughan to the Highway 401/407 ETR interchange through Caledon and Brampton, says the Ontario Ministry of Transportation. Ontario awarded the first construction contracts on August 27, 2025, and the ministry’s Process and Timeline page lists no opening date for the highway.
This Brampton Homes guide explains where Highway 413 will run through Caledon and Brampton and what is being built, then looks at what research can and cannot say about home values near the route. Brampton Homes is run by Aura Key Realty, a real estate team operating under RE/MAX EXCELLENCE REAL ESTATE, BROKERAGE.
Highway 413 is past the planning stage: early work is underway, the corridor is designated, and the final environmental report is posted.
The Ministry of Transportation sets the route and can acquire the land, while Brampton and Caledon handle land use planning on either side of the corridor. For owners and buyers, the practical parts are the checks near the corridor and those local plans. If something is unconfirmed, I say so.
Key Takeaways
- The province has designated the Highway 413 corridor.
- Properties near the corridor now need Ministry of Transportation (MTO) permits for some development.
- The province says drivers who travel the full length will save time each way at rush hour.
- Effects on home values depend on distance: access helps, while noise and construction hurt.
- Check your address on the official map before you buy or sell.
Where Will Highway 413 Go and How Does It Affect Home Values?
The route has an official answer: the ministry’s preliminary design runs Highway 413 through York, Peel and Halton Regions. For home values, the useful tools are research on other highways and a close look at each home.
Where the Highway 413 Route Runs
I start with location, because when you buy a home, you also buy its location. The Ministry of Transportation’s project site says Highway 413 will run from Highway 400, between King Road and Kirby Road, to the Highway 401/407 ETR (Express Toll Route) interchange in Mississauga, Milton and Halton Hills.
Along the way, it passes through Vaughan, Caledon, Brampton and Halton Hills, according to the Impact Assessment Agency of Canada project registry.
The project also includes extensions of Highway 410 and Highway 427 that connect to the new highway. A transitway will run alongside it in a separate corridor dedicated to public transit, and it will need its own environmental assessment, according to the same ministry page.
This route is the province’s preliminary design, the version set out in its final environmental report. For drive times to Vaughan, Caledon, Milton and Mississauga, see cities near Brampton.
Where to See the Official Highway 413 Route
The official version is the interactive map on the Highway 413 project site, run by the Ministry of Transportation. It shows the preliminary design reflected in the final Environmental Impact Assessment Report, the report prepared under the Highway 413 Act, 2024.
To check a home, find its street on the map and compare the property with the corridor. The ministry’s map note says the map is accurate to March 12, 2026 and based on the preliminary design, so a definite answer about one property has to come from the ministry itself.
If your property may be affected, contact MTO through its property acquisition page.
Highway 413 Interchanges in Brampton and Caledon
An interchange is where ramps connect a highway to another highway or a major road, as the ministry’s final report page puts it. Section 4.3.2 of the ministry’s final environmental report describes each local road interchange, listed here in the order the report gives them.
- Winston Churchill Boulevard: full interchange, with all ramps
- Bovaird Drive: full interchange; its underpass is an early works project
- Mayfield Road: full interchange
- Chinguacousy Road: full interchange
- Highway 10 (Hurontario Street): full interchange; its underpass is an early works project
- Bramalea Road: full interchange (final EIAR, section 4.3.2.6)
- Mayfield Road at Highway 410: the existing interchange, changed to connect to the Highway 410 extension
- Airport Road: full interchange
- The Gore Road: partial interchange
- Humber Station Road: full interchange
- Highway 27: entrance and exit ramps in both directions, on a different ramp layout
- Weston Road: partial interchange, because a full one is not technically feasible so close to the Highway 400 interchange
- Major Mackenzie Drive at Highway 427: the existing partial interchange, rebuilt as a full interchange for the Highway 427 extension
The highway also connects to Highway 401/407 ETR, Highway 410, Highway 427 and Highway 400 through highway-to-highway interchanges, described in section 4.3.1 of the same report. All of this is preliminary design, and detail design will include further refinements, so ramps can still change.
The homes for sale in Bramwest show what is listed in western Brampton now.
What Highway 413 Means for Home Values
One study of single-family home sales across the Greater Toronto and Hamilton Area, Regional transport accessibility and residential property values, found that access to the regional transport network plays a significant role in home values, beyond being near a station or highway.
Older Canadian and American studies point the other way: a survey of nine of them in the Journal of Transport Economics and Policy found that traffic noise on a main highway lowered house prices.
A study of two new highways in the Netherlands, The effects of highway development on housing prices, found both effects: access raised prices while noise and traffic lowered them, and the net effect was generally positive, even before the highways were finished.
These studies looked at other places and other highways, so none tells you which effect wins on a particular street near Highway 413. Any price claim here is a projection. I focus on what is confirmed for the specific home.
| Benefits | Proximity risks |
|---|---|
| Faster access to Highways 400, 401 and 407 | Traffic noise for homes close to the route |
| New jobs, according to the province | Construction work along the route before it opens |
| Shorter commutes across the western GTA | Land taken for the route and interchanges |
Sources: benefits from Highway 413 Project Benefits, Government of Ontario; risks from the noise studies above, the Early Works page and the 2025 Ontario Budget cited in this guide.
Current Brampton sale prices by property type are on the Brampton Market Watch, which reports Toronto Regional Real Estate Board figures each month.
When Will Highway 413 Be Built and Open?
The early works are under way. On August 27, 2025, the Ontario government said it had awarded the first two contracts to begin construction.
According to that release, work was beginning to resurface Highway 10 in Caledon in preparation for a new bridge over the future highway, and crews would soon begin upgrades at the Highway 401/407 interchange.
In Ontario Advancing Work on Highway 413, published on December 9, 2025, the Ministry of Transportation said it was seeking proposals to design an extension from Highway 410 at Countryside Drive north to Highway 413, and from Highway 413 west to Highway 10.
The same release said the province had recently completed the Highway 401/407 interchange upgrades.
In Ontario Taking Next Steps to Build Highway 413, published on September 1, 2026, the ministry said Ontario “has also awarded a contract for a construction manager for the Highway 413 central contract, including the 410 Extension.”
The release adds that the detail design contract for the Highway 413 central contract was awarded in June 2026, and the program management contract for overseeing the overall design, coordination and construction of the highway in July 2026.
The same release says Ontario “has issued a notice of procurement to design and build the east section of Highway 413 as well as the Highway 427 Extension.”
According to the release, a request for proposals was to follow in fall 2026, covering Highway 400 to west of The Gore Road and the Highway 427 extension from Major Mackenzie Drive north to Highway 413.
In a design-build contract, one team both designs and builds the work.
The ministry’s Process and Timeline page (checked October 13, 2026) lists no opening date; its milestones say that, subject to funding and approvals, the project will go through detail design and procurement before construction begins.
The ministry’s final report page says the timing of construction “depends on numerous factors,” including funding, the procurement method, environmental clearances and permits, and property acquisition.
The 2026 Ontario Budget (checked October 13, 2026) lists no total cost for Highway 413 and says the province is “working in consultation with the industry on a plan to deliver Highway 413 in multiple sections.” Estimates from other sources are not official, so I leave them out.
Has Highway 413 Been Approved?
The Highway 413 Act, 2024, Schedule 3 of Bill 212, exempts work for or related to Highway 413 from Ontario’s Environmental Assessment Act and bars carrying out the project except in accordance with its final Environmental Impact Assessment Report.
The final environmental report is now posted on the project site, after a comment period for an earlier draft.
At the request of both governments, the Federal Court ordered that Canada’s designation of the project for a federal impact assessment be set aside, and the two governments signed a Memorandum of Understanding, according to their joint news release.
When a new request came in to designate the project under the Impact Assessment Act, the President of the Impact Assessment Agency of Canada determined that it does not warrant designation.
Table 6-1 of the final environmental report lists federal authorizations that may be required, under the Fisheries Act, the Species at Risk Act and the Migratory Birds Regulations, 2022.
Will Highway 413 Be Tolled, and How Much Time Will It Save?
The Get It Done Act, 2024 changed Ontario’s highway law so that no toll may be charged for travel on a highway where the province is the road authority, unless an Act authorizes it.
In the legislature on March 4, 2024, Minister of Transportation Prabmeet Sarkaria described Highway 413 as “a new 400-series highway that will be toll-free,” according to Hansard.
On time savings, the ministry’s final report page says commuters may save up to 30 minutes when “travelling the full length of Highway 413 during rush hour.”
A much smaller number also circulates, 30 seconds, and the ministry’s own project site says that figure comes from a 2017 study of “average time savings across the entire Greater Golden Horseshoe,” the wider region around Toronto, including “every trip on every road in every region.”
These numbers answer different questions. One describes a rush hour driver on the full route; the other averages a saving over trips across an entire region, many of which may never use Highway 413. That is why I would not plan a move around either figure on its own.
Buyers who would rather commute by train can compare the GO stations in Brampton, with trip times and parking.
What Should Buyers and Owners Check Near the Highway 413 Route?
On November 27, 2025, Ontario designated the Highway 413 corridor under the Public Transportation and Highway Improvement Act, a step that also released properties not expected to be affected from the areas the ministry had been studying.
Properties near the corridor now need permits before certain developments and activities, according to the ministry’s Process and Timeline page.
The ministry’s Highway Corridor Management offices issue these permits. Near provincial highways, a building and land use permit can be needed for residential construction, renovating a house, drilling a well or installing a swimming pool. Ask the ministry which rules apply to each property.
The 2025 Ontario Budget says the province needs to acquire more than 500 properties for construction.
Expropriation is “a legislated process that enables the ministry to acquire property without an agreement with the owner, while still ensuring that owners are compensated,” says the ministry’s property acquisition page.
Under Ontario’s Expropriations Act, compensation is based on the land’s market value, plus damages for disturbance, for harm to remaining land and for special difficulties in relocating.
Under section 25 of the Act, the province must offer the owner full compensation, and immediate payment of the full market value it has assessed, before it takes possession.
If the two sides cannot agree on the amount, section 26 lets either one ask the Ontario Land Tribunal to decide it.
The ministry’s milestones include meetings with potentially affected landowners, and it asks owners for Permission to Enter so its crews can do fieldwork on their land. According to the ministry’s Permission to Enter page, receiving that request “does not mean we will need to acquire your property.”
The same page says the owner receives a form by letter or email, signs it and returns it within three weeks, and crews give notice three to five business days before entering.
The Building Highways Faster Act, 2024 adds rules for priority highways, including Highway 413. Under that Act, owners cannot apply to change the possession date in a notice of possession, and obstructing a site inspection or the taking of possession is an offence.
Imagine you find a home you like that backs onto the corridor. Before your offer becomes binding, work through these checks with your power team: your REALTOR®, your real estate lawyer and your lender.
- Find the home on the ministry’s interactive map, which shows where the preliminary design runs in relation to the property.
- Ask the ministry whether the property sits in or near the designated corridor, and which activities need its permit. The answer affects what you can build or change on the property later.
- Ask the seller whether any letter from the ministry has arrived, such as an invitation to a landowner meeting, a Permission to Enter request or an expropriation notice.
- Read the City of Brampton or Town of Caledon plan for the area. It shows what else is planned nearby.
- Have a real estate lawyer review the ownership records and any ministry letters before your offer becomes binding. Permit and expropriation questions are legal questions, so the advice should come before you commit.
- For a home backing onto the corridor, weigh better access against traffic noise. Only you can judge which matters more for your household.
Owners near the route can request a free home evaluation: a value estimate based on recent MLS® sales, prepared manually and reviewed by a Broker.
Check how Highway 413 affects your home’s value
First-time buyers have these highway checks in addition to the usual steps of a first purchase. The first-time home buyer guide covers down payments, rebates and the other steps.
What Is Planned Around Highway 413 in Brampton and Caledon?
In Brampton, the Heritage Heights Secondary Plan, the City’s detailed land use plan for that area, is approved, following an Ontario Land Tribunal decision, according to the City of Brampton’s Heritage Heights Transportation Master Plan boards.
The City paused its Bram West Secondary Plan Review while the highway design was uncertain, then resumed it once the design and route were clarified.
The guide to living in Bramwest describes the area today, from schools to the parks along the Credit River.
In Caledon, the province approved the Future Caledon Official Plan, the town’s long-term plan for growth and development through 2051.
Peel Region’s planning changes took effect on July 1, 2024, when it lost its planning responsibilities, according to a provincial backgrounder, which leaves land use near the corridor to Brampton and Caledon.
For buyers considering a new build, pre-construction homes in Brampton explains deposits, financing, incentives and warranties.
Brampton communities lets you compare areas across the city by homes for sale, schools, transit, parks and amenities.
Who Decides What Happens Next on Highway 413?
When the corridor was designated, the Ministry of Transportation “formally identified the specific route of the new highway” and has “the authority to acquire this land as needed,” says its Corridor Designation page.
The ministry also awards the design and construction contracts. Federal departments review any fish, species at risk and migratory bird permits, while Brampton and Caledon set land use plans near the corridor.
The table below shows where each part of the project stands and who decides it.
| Part of the project | Where it stands | Who decides | Source |
|---|---|---|---|
| Route and design | 52 km corridor from Highway 400 in Vaughan to the Highway 401/407 ETR interchange, plus the Highway 410 and Highway 427 extensions and a separate transitway corridor; preliminary design | Ministry of Transportation | Ministry project site |
| Provincial approval | Standard environmental assessment replaced under the Highway 413 Act, 2024; final Environmental Impact Assessment Report posted | Legislature of Ontario; Ministry of Transportation | Bill 212; ministry final report page |
| Federal review | Designation set aside, then not designated; federal fish, species at risk and migratory bird permits may be required | Government of Canada | Impact Assessment Agency of Canada registry; final report, Table 6-1 |
| Corridor protection | Corridor designated on November 27, 2025; permits needed nearby; some study-area properties released | Ministry of Transportation | Ministry Process and Timeline page |
| Early works | Underway; first contracts awarded on August 27, 2025; Highway 401/407 interchange upgrades completed | Ministry of Transportation | Early Works page; releases of August 27, 2025 and December 9, 2025 |
| Central section with the Highway 410 extension | Detail design and construction manager contracts awarded | Ministry of Transportation | Provincial release, September 1, 2026 |
| East section with the Highway 427 extension | Notice of procurement issued for a design-build contract | Ministry of Transportation | Provincial release, September 1, 2026 |
| Opening date and total cost | No opening date listed; no total cost listed (checked October 13, 2026) | Province of Ontario | Process and Timeline page; 2026 Ontario Budget |
| Tolls | Prohibited on provincial highways unless an Act authorizes one | Legislature of Ontario | Get It Done Act, 2024 |
Sources: Highway 413, Process and Timeline and final report, Ontario Ministry of Transportation; Bill 212 and Bill 162, Legislative Assembly of Ontario; project registry, Impact Assessment Agency of Canada; releases of August 27, 2025, December 9, 2025 and September 1, 2026, Government of Ontario; 2026 Ontario Budget.
Frequently Asked Questions
Does Highway 413 Go Through Brampton and Caledon?
Has Construction on Highway 413 Started?
When Will Highway 413 Open?
Will Highway 413 Be a Toll Road?
Will My Property Be Expropriated for Highway 413?
Will Highway 413 Raise Home Prices in Brampton or Caledon?
Conclusion
Next to watch are the east section contract, the detail design work and any official opening date or cost.
For any one home, weigh what is confirmed for that property and the plans around it over any forecast about the highway. A projection is not a fact about your street.
Contact the team to discuss how the Highway 413 route affects a home you are buying or selling in Brampton or Caledon. We can go through the official map and the local plans for that address with you.
Disclaimer: This article is for informational purposes only and does not constitute legal, tax, or financial advice. Laws and regulations may change over time. Always consult a qualified real estate lawyer or other appropriate professional before making any decisions.